How to Get Started with an ADU in Los Angeles

Cuckoo Residence by YDS Architects
← ResourcesApr 19, 20232 min read

Updated October 2026

Start with the lot, not the floor plan. What your lot can hold decides the type, the size and the budget. Everything after that is sequence.

The short version

  • Cities must approve or deny a complete ADU application within 60 days. Detached ADUs on a qualifying preapproved plan get a decision within 30 days.
  • A city can’t cap an ADU below 850 sf for a studio or one-bed, or 1,000 sf for more bedrooms.
  • Side and rear setbacks for a new ADU can’t exceed 4 ft.
  • No impact fees on ADUs under 750 sf.
  • No parking required within a half mile of public transit, and none to replace a garage you convert.

1. Check the lot

Pull your zoning, lot size, easements and any hillside, fire or historic overlays. In the City of LA, ZIMAS shows most of this. Note utility locations and slope. These decide where a unit can go and what it costs to connect.

2. Pick the type

  • Detached: most privacy and flexibility. At least 16 ft high, 18 ft within a half mile of major transit.
  • Attached: shares a wall with the house. Up to 25 ft, or the zone limit if lower.
  • Conversion: a garage or part of the house. Usually the lowest cost.
  • JADU: up to 500 sf inside the main house.

3. Design and price it

Test two or three options side by side before committing. Get a construction estimate on schematic drawings, not on a hunch. Bring in structural, Title 24 energy and, on slopes, civil engineering early.

4. Permit and build

Submit a complete set. Incomplete sets restart the clock. Expect plan check corrections. Once permitted, a contractor builds to the set, the city inspects in stages, and you get final sign-off.

What to watch out for

  • Utility connections and sewer laterals can cost more than expected.
  • Fire zones and hillside rules add requirements.
  • If the lot is big enough, an ADU may not be the best use. Check that first.

How we use it

We run every lot through this same order, and sometimes it points past an ADU. Cuckoo Complex in San Diego is a six-unit building shaped by light, air and courtyards. Mariposa Complex in Altadena uses SB 1123 for three homes on a shared driveway, each with an attached ground-floor ADU. See SB 684 / SB 1123 and our multifamily work.

Sources: HCD ADU fact sheet (April 2026), Furman Center on AB 1332.

Cuckoo Complex, San Diego

From our portfolio

Density shaped by light, air and courtyards.

View project →

Have a lot in mind?

Send us the address and we’ll tell you what it can hold. Book a free consultation → · Follow @ydsarch on Instagram

Picture of Yifu Pan

Yifu Pan

Yifu Pan, founder and principal architect of YDS Architects, is revolutionizing SoCal architecture. With a Master’s degree from USC, a decade of experience, and a deep understanding of architectural design, he provides high-quality, family-centered solutions. His commitment to affordable housing and community-beneficial commercial spaces showcases his passion for design.

Leave a Reply

About YDS Architects

YDS Architects is a Los Angeles architect collective of designers, permit expediters, and planners specializing in modern residential and commercial design across Southern California — including ADUs and multifamily housing.

Los Angeles Fires Resources

Mariposa Residence, Altadena, by YDS Architects
Planning a rebuild or a new project? Book a free consultation · 626-660-0206

Recent Posts

Follow Us

Get a free consult with a Los Angeles architect.

Start a project →or call 626-660-0206 · info@ydsarch.com
Scroll to Top