ADU Timeline in California: Process and Review Times

← ResourcesSep 3, 20242 min read

Updated October 2026

An ADU runs through four stages: feasibility, design, permits and construction. State law fixes the city’s review clock. Design and construction time depend mostly on you, your site and your contractor.

The short version

  • Since January 1, 2026, the city must tell you within 15 business days whether your application is complete, and list what’s missing (SB 543).
  • Once the application is complete, the city has 60 days to approve or deny it. Denials must come with written reasons.
  • Every city must offer pre-approved ADU plans, required since January 1, 2025 (AB 1332). Using one shortens design.
  • Plan-check corrections, not the city’s clock, are what usually stretch a schedule.

The four stages

  1. Feasibility. Zoning, setbacks, utilities, slope, easements, fire zone. This decides whether the unit fits and what kind fits.
  2. Design. Layout, structure, energy (Title 24) calculations and the full drawing set. Custom design takes longer than a pre-approved plan.
  3. Permits. Submittal, completeness check, plan review, corrections, then permit issuance after fees are paid. Some sites also need fire, sewer or utility sign-offs.
  4. Construction. Site work, foundation, framing, rough-in inspections, finishes and final inspection. A conversion moves faster than a new detached unit.

What slows projects down

  • Incomplete submittals and slow responses to corrections.
  • Utility upgrades: a new electrical panel or sewer connection can add weeks.
  • Hillside, fire-zone or protected-tree sites that need extra reports.
  • Unpermitted existing structures. AB 2533 (2025) helps legalize ADUs built before January 1, 2020, but the work still has to pass inspection.

How we use it

The same steps apply to bigger moves. Our Diamond Bar Three-Lot concept puts three homes where one used to fit. On the SB 684 and SB 1123 path, a qualifying small-lot subdivision also gets a 60-day ministerial decision. On our entitled Motor Complex in Culver City, an SB 684 split turned one 7,000 sf lot into four.

Diamond Bar Three-Lot, three homes in a row, YDS concept
Diamond Bar Three-Lot (concept). Three homes where one used to fit.
Diamond Bar Three-Lot

From our portfolio

Three homes where one used to fit.

View project →

Have a lot in mind?

Send us the address and we’ll tell you what it can hold. Book a free consultation → · Follow @ydsarch on Instagram

Picture of Yifu Pan

Yifu Pan

Yifu Pan, founder and principal architect of YDS Architects, is revolutionizing SoCal architecture. With a Master’s degree from USC, a decade of experience, and a deep understanding of architectural design, he provides high-quality, family-centered solutions. His commitment to affordable housing and community-beneficial commercial spaces showcases his passion for design.

Leave a Reply

About YDS Architects

YDS Architects is a Los Angeles architect collective of designers, permit expediters, and planners specializing in modern residential and commercial design across Southern California — including ADUs and multifamily housing.

Los Angeles Fires Resources

Mariposa Residence, Altadena, by YDS Architects
Planning a rebuild or a new project? Book a free consultation · 626-660-0206

Recent Posts

Follow Us

Get a free consult with a Los Angeles architect.

Start a project →or call 626-660-0206 · info@ydsarch.com
Scroll to Top